Data and source cutoff: November 23, 2026, 5:50 a.m. CT. All times are Central Time (CT). Labels in this article: Fact = stated in a published study or an official statistical release; Analysis = EconShift’s reading of how those sources line up; Scenario = a study’s own conditional projection, not an EconShift forecast. This article sets out published ranges and their assumptions. It gives no probability for any 2030 outcome, and it makes no price, security or policy recommendation.
Three different things, often reported as one
Analysis. Coverage of AI data centers and the U.S. power grid tends to blend three separate measures: electricity that data centers are already using, projects that have been announced but are not necessarily built or connected, and dollars being spent on construction. Each answers a different question. This article reads recent published studies one measure at a time, because a number from one cannot stand in for another.
Two further distinctions run throughout: a study of the largest “hyperscale” facilities is not a study of all U.S. data centers, and a 2030 figure is a scenario built on stated assumptions, not a measured result.
Current use: a hyperscale sample is not the national total
Fact. A peer-reviewed study published in Nature Sustainability on November 16, 2026, “Assessing the carbon emissions and energy consumption of US hyperscale data centres,” compiled facility-level information on 403 U.S. hyperscale data centers operating between May 2024 and April 2025. Across facility-load scenarios, the abstract estimates these facilities consumed roughly 68–99 TWh of electricity. Under the central scenario, demand was about 82 TWh, which the authors put at about 1.8% of total U.S. electricity consumption.
Fact. The same abstract associates that use with roughly 21–31 million metric tons of CO2 (central scenario about 25.7 Mt), under a location-based, total-output, balancing-authority attribution method. It reports that roughly 54% of attributed generation came from fossil fuels, and an electricity-weighted carbon intensity of about 314 gCO2/kWh for these facilities, compared with a U.S. total-output average of about 348 gCO2/kWh.
Analysis. Two cautions. First, 1.8% is the share for this sample of 403 hyperscale sites; it is not the share of all U.S. data centers. Second, an earlier preprint version of the paper gives different emissions and carbon-intensity figures. We use only the published version of record, and only its abstract; the full article is behind a paywall and we have not read it.
Fact. Two broader studies cover U.S. data centers as a whole. EPRI’s Powering Intelligence 2026 (February 2026) estimates 2024 U.S. data center electricity use at 177–192 TWh, or 4% to 5% of U.S. electricity, with nominal IT capacity of 35–44 GW. Lawrence Berkeley National Laboratory’s United States Data Center Energy Usage Report: 2025 Update (June 2026) puts 2024 use at 192 TWh, or 4.7% of total U.S. electricity consumption, and states that cryptocurrency mining is not included in its scope.
Analysis. The EPRI and LBNL 2024 figures are close but come from different methods and definitions; neither revises or confirms the other. The Nature Sustainability figure of about 82 TWh describes a subset of facilities and cannot be added to, or subtracted from, the national estimates.
2030: scenarios built on project realization
Scenario. EPRI’s 2030 range depends on how many planned and announced projects become fully operational. Its executive summary gives roughly 380 to 790 TWh by 2030; the report body (Figure 5) gives 383 TWh (Low), 596 TWh (Medium) and 793 TWh (High). EPRI puts the data center share of U.S. electricity at 9% to 17% in 2030, up from 4% to 5% today. Nominal IT capacity reaches 56 GW, 96 GW and 132 GW in the three scenarios.
Fact. The scenarios rest on explicit assumptions. Low assumes most projects under construction and one-fourth of those in advanced planning are fully operational by 2030. Medium assumes all projects under construction, 75% of those in advanced planning and 10% in early planning. High assumes all projects under construction or in advanced planning, plus 30% of those in early planning. EPRI writes that the scenarios “are not necessarily equally likely,” that many announced projects are speculative with limited public disclosure, and that there is fundamental uncertainty about adoption of generative AI.
Scenario. EPRI also gives a state-level scenario for Virginia: data centers there already use more than 20% of the state’s electricity, and that share could reach 39% to 57% by 2030 in its scenarios. These are Virginia figures, not national ones. EPRI separately cites IEA (2025) and JLL (2026) for an estimate that AI workloads account for about 15–25% of data center electricity today; we have not opened those underlying sources.
Scenario. LBNL’s Reference Case for 2030 is 649 TWh, which the report says represents 11.8% of forecasted 2030 U.S. electricity use as presented in the North American Electric Reliability Corporation’s (NERC) 2025 Long-Term Reliability Assessment. Its compounded uncertainty range runs from 521 TWh (9.5%) to 843 TWh (15.3%). LBNL also reports a 2028 Reference Case of 464 TWh; that is a 2028 figure and should not be read as a 2030 estimate.
Analysis. The 11.8% share uses NERC’s projection of total 2030 U.S. electricity use as its denominator, as cited by LBNL. We have not opened the NERC assessment itself. EPRI’s 9%–17% uses EPRI’s own modeled demand. The two ranges overlap, but different methods, scope and denominators mean they do not “validate” one number. The High case in either study is not a baseline.
| Study | Coverage | Period | Electricity | Share of U.S. use |
|---|---|---|---|---|
| Nature Sustainability (Nov. 16, 2026) | 403 hyperscale data centers | May 2024–Apr. 2025 | 68–99 TWh; central ~82 TWh | ~1.8% (sample only) |
| EPRI, Powering Intelligence 2026 (Feb. 2026) | All U.S. data centers | 2024 estimate | 177–192 TWh | 4%–5% |
| LBNL, 2025 Update (June 2026) | All U.S. data centers, excl. crypto mining | 2024 estimate | 192 TWh | 4.7% |
| EPRI scenarios | All U.S. data centers | 2030 Low / Medium / High | 383 / 596 / 793 TWh | 9%–17% |
| LBNL scenarios | All U.S. data centers, excl. crypto mining | 2030 Reference (range) | 649 TWh (521–843) | 11.8% (9.5%–15.3%), vs. NERC forecast as cited by LBNL |
Table note: rows come from different studies with different coverage, methods and denominators. They cannot be added together and should not be read as one time series or as a consensus estimate.
Construction spending: dollars, not megawatts
Fact. The U.S. Census Bureau’s construction spending release for September 2026 (CB26-176, November 2, 2026) puts private spending on data center construction at a preliminary $96.462 billion at a seasonally adjusted annual rate (SAAR), in current dollars not adjusted for price changes. That compares with $50.700 billion in September 2025, $37.576 billion in September 2024 and $14.571 billion in September 2022. Data centers are a subcategory of Office construction in the Census tables. The September figure is preliminary and is scheduled to be revised when October data are released on December 1, 2026.
Analysis. Construction spending measures dollars put in place, at an annual rate. It does not convert into megawatts connected to the grid or terawatt-hours consumed, and it cannot be used to confirm any 2030 electricity scenario. It does not show when, or whether, those facilities will draw power.
Where timing and policy enter
Analysis. Timing sits in the gap between announced projects and operating load. In EPRI’s framework, how much of the planned pipeline is operating by 2030 is what separates its Low and High cases.
Fact. EPRI’s own discussion notes that supply chain bottlenecks, from equipment manufacturing to permitting and siting, could constrain additions of both generation and transmission capacity, and that interconnecting large new loads can require significant grid upgrades in some cases. This is EPRI’s analysis, not a filing or plan from a grid operator.
Analysis. For readers following energy and data center policy, the impact pathway is straightforward: decisions that speed up or slow down permitting, transmission and new generation would affect how quickly announced projects can become operating load, and therefore which part of the published ranges is more relevant. This article takes no position on any specific policy, subsidy or approval reform, and offers no view on its legality.
Not covered. We did not open, and do not cite, Energy Information Administration data center series, NERC source documents, utility or grid operator load filings, or secondary news reports. We make no electricity price, company or grid-reliability call.
Three things to keep separate
- Operating use versus announced projects. The 2024 estimates describe use; announced projects drive the 2030 scenarios and are not operating capacity.
- Hyperscale sample versus all data centers. The Nature Sustainability 82 TWh and 1.8% apply to 403 hyperscale sites, not the whole sector.
- Scenarios versus forecasts. EPRI’s 383–793 TWh and LBNL’s 521–843 TWh are conditional ranges with stated assumptions, not probabilities. Construction dollars do not settle which one is right.
This article is for general information and research purposes only. It is not investment, legal or business advice, and it contains no recommendation to buy, sell or hold any security. See our Methodology and About pages.
Sources
- Guidi, G., Dominici, F., et al., “Assessing the carbon emissions and energy consumption of US hyperscale data centres,” Nature Sustainability, published November 16, 2026, DOI 10.1038/s41893-026-01985-7 (version-of-record abstract only): https://www.nature.com/articles/s41893-026-01985-7
- EPRI, Powering Intelligence 2026: Updated Scenarios of U.S. Data Center Electricity Use and Power Strategies, February 2026 (PDF report): https://powering-intelligence.epri.com/
- Smith et al., Lawrence Berkeley National Laboratory, United States Data Center Energy Usage Report: 2025 Update, June 2026, LBNL-2001758, OSTI 3374245: https://doi.org/10.71468/P1RP4F
- U.S. Census Bureau, “Monthly Construction Spending, September 2026” (CB26-176), November 2, 2026: https://www.census.gov/construction/c30/pdf/release.pdf ; private construction SAAR time series (Data center column): https://www.census.gov/construction/c30/xlsx/privsatime.xlsx